Rebar Estimation Report ? US Sample Project 1

Comprehensive rebar estimation and bar bending schedule for a multi-building commercial complex comprising three building areas (1A, 1B, EA 2), a trash enclosure slab, and CMU walls. The project was organised into five bid items covering spread footings, grade beams, slab-on-grade, elevator pits, and masonry walls. Total estimated rebar weight: 114,213 lbs (approx. 51.8 tonnes) across all bid items.

Scope of Work

Rebar estimation and BBS for 5 bid items. Segments: spread footings (PFTG), grade beams (GBMS), slab-on-grade (SOG), elevator pits (FDN), trash enclosure slab (SLAB), and CMU walls (WALL). Rebar sizes #3, #4, #5, #6. Lap splice: 48D. Stock lengths: #3 = 20'-0", #4???#6 = 30'-0". Included items: standees, bury bars, carrier bars, and wall spreader bars. Excluded: welded bars, joint smooth dowels, and utility structures.

Project Details
Category Rebar Estimation
Client Confidential
Location San Francisco, CA
Country USA
Year Completed 2023
Steel Tonnage 51.8 Tonnes
Standards ACI 1983 | Grade 60 Rebar | 48D Lap Splice
Status Completed

Need a similar project delivered?

Get a Free Quote Contact Us
UPSILON STEEL Bot
Online
👋 Hello! I'm the UPSILON STEEL assistant. How can I help you today?
I can answer questions about our rebar detailing, BBS, estimation, BIM, and CAD services.